On site now

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah

Job 37EW 22 Jul – 3 Sep 2026 12 updates 43 photos Tanah Merah

These are working photos from an active Larry Contractors renovation, updated as the job moves. For finished work, see the portfolio.

3 Sep 7 days ago 4 photos

Sliding gate is up at 37EW. The frame was welded on site before it went on. Solar is in as well, lifted up to the roof by crane. Toilets and shower sets are installed in both bathrooms. Moving closer to completion.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 3 Sep, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 3 Sep, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 3 Sep, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 3 Sep, photo 4
29 Aug 13 days ago 5 photos

Painting has started at 37EW. The ceilings inside and the external walls now have their coat on, scaffold still up. Solar panels go in next week. Four months in, and the long wait now is carpentry and windows.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Aug, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Aug, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Aug, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Aug, photo 4 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Aug, photo 5
27 Aug 27 Aug 2026 1 photo

Rear courtyard tiling at 37EW. Large-format grey tiles laid right across the yard. The access covers are cut in so the grout lines carry straight through them. Work around the courtyard is still going on.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 27 Aug, photo 1
18 Aug 18 Aug 2026 5 photos

Exterior flooring at 37EW is about 90% done. The last tiles are down with the levelling clips still on. Inside we have started the self-levelling screed, ready for vinyl flooring.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 18 Aug, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 18 Aug, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 18 Aug, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 18 Aug, photo 4 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 18 Aug, photo 5
15 Aug 15 Aug 2026 1 photo

Planning stage for a solar PV system. This is the roof plan showing where the panels will sit. Layout is set out before any install work starts.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 15 Aug, photo 1
13 Aug 13 Aug 2026 2 photos

Laying floor tiles across the courtyard on this A&A job. Every gradient is measured so water runs off the way it should. Screed bed goes down first, then the tiles follow the fall. Working doubly hard to keep on schedule.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 2
13 Aug 13 Aug 2026 3 photos

Internal level 1 tiling is nearly done. Large format tiles laid with levelling clips to keep them flat. Now we move to the external works, rendering and waterproofing the structure at the front. Job at 37 Eastwood Way.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 3
13 Aug 13 Aug 2026 1 photo

Laying the floor tiles in this courtyard. Big-format tiles with levelling clips to keep them flat. Left the openings for the services and finishing the rest this week.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 13 Aug, photo 1
8 Aug 8 Aug 2026 1 photo

Exterior tiling works, job 37EW. Large tiles laid out with levelling clips to hold the gradient and keep the alignment matched across the floor. Working on it every day to get it finished. Levels checked as we go.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 8 Aug, photo 1
29 Jul 29 Jul 2026 6 photos

Work in progress on this house. Walls plastered, bathroom tiling going in with levelling clips still on, and the staircase balustrade set. Floor is almost ready for screed to level up before finishing and paint works.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 4 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 5 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 29 Jul, photo 6
26 Jul 26 Jul 2026 5 photos

Renovation works on a 3-storey semi-detached house. Over three months of masonry, partition, electrical and plumbing work. Here you can see the ceiling being built up and the floor tiling going in with levelling clips still on. Job is running well and we may finish before the November 2026 completion date.

— Larry @larryhoo89

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 26 Jul, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 26 Jul, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 26 Jul, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 26 Jul, photo 4 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 26 Jul, photo 5
22 Jul 22 Jul 2026 9 photos

Work in progress on job 37EW. We are forming the window and door openings and smoothing the wall around them ready for installation. Same job we are laying the floor tiles, set out with levelling clips before grouting. Wiring is still run loose while the rooms are being finished.

Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 1 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 2 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 3 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 4 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 5 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 6 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 7 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 8 Renovation Works On A 3-Storey Semi-Detached House in Tanah Merah — job 37EW, 22 Jul, photo 9